Important Notice: Road Repair

Jamie Bell Uncategorised

Even Notre Dame Drive is doing a little Spring Cleansing, read below to find out how to access and exit the clinic in the coming months.

The Regional Municipality of Waterloo is planning the reconstruction of Notre Dame Drive from the railway tracks to Highway 7&8. Construction is scheduled to commence on or about Monday May 1, 2017 and will continue until Fall 2017.

To Access the Clinic:

Stage 1 – Notre Dame Drive from Highway 7&8 to Snyder’s Road:

Construction will be completed one half of the road at a time, maintaining northbound traffic only on Notre Dame Drive. Access from Highway 7&8 will be maintained, but access to Highway 7&8 (i.e. southbound on Notre Dame Drive) will be closed. This stage of construction is expected to last approximately 2 months. During this closure southbound traffic will be maintained from Snyder’s Road to the Blue Moon parking lot. On-street parking will be unavailable. Local pedestrian and vehicle access to residents and businesses will be maintained at all times. It is preferred that if at all possible, local access be from the south using the open northbound lane on Notre Dame Drive.

Stage 2: Snyder’s Road from Notre Dame Drive to 350 m west of Notre Dame Dr.:

This leg of Snyder’s Road will be closed to through traffic starting in early July 2017. Construction is expected to last approximately 4-5 weeks for this stage. On-street parking will be unavailable. Local pedestrian and vehicle access to residents and businesses will be maintained at all times.

Stage 3: Notre Dame Drive from Snyder’s Road to the Railway tracks:

This leg of Notre Dame Drive will be closed to through traffic starting in early to mid-August 2017. Construction is expected to last approximately 4-5 weeks. On-street parking will be unavailable. Local pedestrian and vehicle access to residents, businesses, side streets, Post Office and the Community Park will be maintained at all times. Stage 4: Snyder’s Road, Notre Dame Drive to Eastern Village Limits: This leg of Snyder’s Road will be closed to through traffic starting approximately mid-September 2017. Construction is expected to last approximately 4-5 weeks. On-street parking will be unavailable. Local pedestrian and vehicle access to residents, businesses, and the Church will be maintained at all times.

To leave the Clinic:

You will need to exit Northbound onto Notre Dame Drive.

Please feel free to call us if you need any help getting to the Clinic. Thank you for your patience.